The first one is a title for start up the power plant after along time as the turbine is cool & our indication is the first stage temperature as actually it is less than120-150°C according to turbine design
The second one is the procedure to start up the power plant after a few hours after shut down in this kind the first stage temrature is over280°C (according to turbine design)
Cold start is start the system without heating