You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram,?

your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following BEST describes what this type of input is called?

 

A. Mandatory dependency

B. Discretionary dependency

C. External dependency

D. Heuristic

user-image
Question added by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants
Date Posted: 2015/08/05
Muhammad Qasim
by Muhammad Qasim , Assistant Procurement Manager , National Institute of Cardiovascular Diseases-Karachi Pakistan

Heuristic 

RAVI GUPTA
by RAVI GUPTA , International Marketing Head , s.k. shoes

Heuristic  i feel this one is the best answer as per the question asked . 

Krishna Mohan Kota
by Krishna Mohan Kota , Manager - Talent Acquisition - Operations & Sales , SRS Consulting Inc

Heuristic - this is a kind of strategy or approach that is based on experience, judgement, and common sense rather than theoretical principles. In this situation, the recommendation is based on the practical premise that getting senior management approval for the data model could improve the overall quality of the software development project, as supported by data from a credible source (the software development journal).

Ahmed Elsamahi MBA office manager  project coordinator C Suite
by Ahmed Elsamahi MBA office manager project coordinator C Suite , Sr. Executive Assistant to CEO , Federal Tax Authority

Certainly! Being part of a construction project team responsible for developing a new stadium is a multifaceted and dynamic role. Here's a breakdown of potential responsibilities and considerations:

  1. Project Planning:

    • Collaborate with architects, engineers, and other stakeholders to develop a comprehensive project plan.
    • Define project scope, objectives, and timelines.
    • Establish a budget and resource allocation plan.
  2. Regulatory Compliance:

    • Ensure compliance with local building codes, safety regulations, and environmental standards.
    • Obtain necessary permits and approvals from relevant authorities.
  3. Budget Management:

    • Monitor and manage the project budget, including tracking expenses and identifying cost-saving opportunities.
    • Work closely with the finance team to ensure financial alignment.
  4. Risk Management:

    • Identify potential risks and develop strategies for risk mitigation.
    • Regularly assess project risks and adjust plans accordingly.
  5. Collaboration with Stakeholders:

    • Coordinate with various stakeholders, including government agencies, contractors, suppliers, and local communities.
    • Communicate project progress, updates, and potential issues to stakeholders.
  6. Construction Oversight:

    • Supervise construction activities to ensure they align with project specifications and quality standards.
    • Monitor progress and address any delays or issues promptly.
  7. Quality Control:

    • Implement a robust quality control program to ensure that the construction meets the specified standards.
    • Conduct regular inspections and quality assurance checks.
  8. Timeline Management:

    • Develop and maintain a project timeline, ensuring that milestones are met.
    • Identify critical path activities and address any delays proactively.
  9. Procurement and Supply Chain Management:

    • Procure materials, equipment, and services needed for construction.
    • Manage relationships with suppliers and contractors.
  10. Safety and Security:

    • Prioritize and enforce safety protocols on the construction site.
    • Implement security measures to protect both personnel and assets.
  11. Sustainability Considerations:

    • Integrate sustainable practices into the construction process, such as energy-efficient systems and environmentally friendly materials.
  12. Technology Integration:

    • Explore and implement construction management software and other technologies to enhance project efficiency and communication.
  13. Community Relations:

    • Engage with the local community to address concerns, foster positive relationships, and ensure the project's acceptance.
  14. Post-Construction Planning:

    • Plan for the transition from construction to stadium operation.
    • Develop maintenance and operational protocols for the completed facility.
  15. Documentation and Reporting:

    • Maintain detailed project documentation.
    • Provide regular reports to stakeholders on project status, budget, and key performance indicators.

Being part of a stadium construction project team requires effective collaboration, adaptability, and a keen eye for detail to ensure the successful and timely completion of the project.

  User   You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram,?   ChatGPT  

Certainly! Developing a network diagram is a critical aspect of project management, especially in the context of a software development project. Here's a step-by-step guide on how you, as the project manager, might approach this task:

  1. Define Project Activities:

    • Work with your project team to identify all the tasks and activities required to complete the software development project. This includes tasks like requirements gathering, design, coding, testing, and implementation.
  2. Sequence Activities:

    • Determine the order in which activities need to be performed. Some tasks may be dependent on others, while some can be performed concurrently.
  3. Create a Task List:

    • Compile a comprehensive list of all the tasks and activities, including their dependencies.
  4. Identify Dependencies:

    • Determine the relationships between tasks. Some tasks may need to be completed before others can start (finish-to-start dependencies), while some may be able to run concurrently (start-to-start or finish-to-finish dependencies).
  5. Estimate Durations:

    • Work with your team to estimate the duration of each task. This involves determining how much time each activity will take to complete.
  6. Draft a Network Diagram:

    • Use a project management tool or draw the network diagram on paper or a whiteboard. Represent tasks as nodes and dependencies as arrows between nodes.
  7. Critical Path Analysis:

    • Identify the critical path, which is the longest sequence of tasks that determines the minimum time needed for the project. Tasks on the critical path must be closely monitored, as any delays will impact the overall project timeline.
  8. Buffer Management:

    • Consider adding buffers or contingency time to critical path tasks to account for uncertainties or potential delays. This helps mitigate risks and ensures that the project remains on schedule.
  9. Review with the Team:

    • Collaborate with your project team to review the network diagram. Ensure that everyone understands the sequence of tasks and the critical path.
  10. Iterate as Necessary:

    • Network diagrams may need to be adjusted as the project progresses. If there are changes to the project scope, resource availability, or task durations, be prepared to update the diagram accordingly.
  11. Communication:

    • Share the finalized network diagram with key stakeholders. This helps everyone involved understand the project schedule and dependencies.

By following these steps, you can create a comprehensive network diagram that serves as a visual representation of the project's schedule and critical path, aiding in effective project management and communication.

Kazi Shahed H Ferdous
by Kazi Shahed H Ferdous , Country Director , Traidcraft Exchange UK (branded as Transform Trade)

A Mandatoty dependency

Usamaa Khan
by Usamaa Khan , Radio Station Coordinator , FM 106.2

Mandatory Dependency

Ene Marian
by Ene Marian , Senior Project Engineer , Sverige Bauer GL AB

  • Precedence diagramming method.
  • Arrow diagramming method.
  • Critical path method.
  • Operational diagramming method.

Fabio Dreyden
by Fabio Dreyden , Regional Operations Manager , Afrikelp

Discretionary dependency

Dada Chandane
by Dada Chandane , International Team Leader & Project Management Expert , Shah Technical Consultants Pvt Ltd

Discetionary dependency. it is project manager's call

Denouvre de Beer
by Denouvre de Beer , IT Delivery Management , Woolworths

Heuristic

Nitin Jain
by Nitin Jain , Lead Data Engineer , Nihilent Technologies

it will be Heuristic dependency.