You are a project manager on a $5,000,000 software development project. While working with your project team to develop a network diagram,?

your data architects suggest that quality could be improved if the data model is approved by senior management before moving on to other design elements. They support this suggestion with an article from a leading software development journal. Which of the following BEST describes what this type of input is called?

 

A. Mandatory dependency

B. Discretionary dependency

C. External dependency

D. Heuristic

user-image
Question added by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants
Date Posted: 2015/08/05
Emad Mohammed said abdalla
by Emad Mohammed said abdalla , ERP & IT Software, operation general manager . , AL DOHA Company

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

B. Discretionary dependency

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

Vinod Jetley
by Vinod Jetley , Assistant General Manager , State Bank of India

 

B. Discretionary dependency

Mohammed Asim Nehal
by Mohammed Asim Nehal , M Asim Nehal & Co , Chartered Accountants

b) is the correct answer..................

 would contact the Sr. Project Manager to get with the Project Sponsor 

Gayasuddin Mohammed
by Gayasuddin Mohammed , Advocate , Practicing Law before High Court at Hyderabad

It is a Discretionary dependency. Option(B) is the answer.