What is the best way of creating a quality WBS for a high rise building?

Is this true that if the WBS is perfect on P6 then the program will be perfect?

user-image
Question added by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture
Date Posted: 2013/08/22
Wilson Loren
by Wilson Loren , Senior Planning Engineer , Saudi Oger Ltd.

Effectively building your WBS, the first time, can be so helpful to everyone in the project team. So it means you need to initiate and define your planning procedure and processes let it be agreed by major stakeholders such as engineering, procurement and construction team. A project wbs can be designed at certain level enough to present project deliverables and define scope of works detailed activities. Contractors may refer to the contract provisions and requirements to ensure compliance. 

Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

It's partly true

coz wbs is the way you understand the typical breakdown of the project 

 

then u proceed to breakdown each wbs elements considering them as individual projects n then you link them together to build yr logic

 