by Arumugam Balasubramani , Senior Mechanical Engineer , WME Engineering Consultants

  1. Approved Technical Submission.
  2. Approved Shop Drawings.
  3. Engineer / Consultant approval for Installation
  4. Elements / Equipment / System - Individual or partial test reports
  5. Manufacturer factory test certificates
  6. Manufacturer and T&C3rd party check list and approval
  7. ITP - Inspection Test Plan
  8. Pre-commissioning Reports of Manufacturer for Equipment / system / element
  9. Test Records data sheet