Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How to draw S curve in primavera software?

user-image
Question added by Shahid Saleem , Businees Developement Engineer/Project Engineer , National Industrial Gas Plants
Date Posted: 2015/09/11
Abid Masood
by Abid Masood , Senior Planner - Manager (PMC) , WSP

Activity usage profile in P6 on the top menu is useful tool for drawing the s-curve in P6.Prior to go to this first add resources i.e manpower,equipment and prices/expenses to the activities in entire schedule. 

More Questions Like This