For most purposes, Submittals and Transmittals are documents exchanged during a building project, typically amongst Architects, Engineers and Construction (AEC) professionals. Most industries considerSubmittals to be more of a preliminary step in the building process, sent with the expectation of forthcoming revisions or a request to be answered therein. Transmittals are typically sent as records, documentation or required materials (such as CAD drawing files) for the project. While Transmittals are still open to revision and collaboration, the sender is usually not seeking such changes or requesting the type of feedback as though it were a Submittal
Submittals are documents that must accompany items being sent, such as sample materials, plans, etc. Submittals typically require a response from the recipient, so it is necessary to track when, and whether a response has been received.
Transmittals are communications that do not accompany any item, and to not require a response. It is not necessary to track whether a response to a transmittal has been received.
Submittal is a document which produce for further review or taking decision for accept or reject.
Transmittal is a letter or detail gives a sender for permanent record.
The transmittal form to record submitting the document, while the submittal is group of documents covered with submittal sheet clarifying the details of the submittal
Submittals are preliminary step in the building process, sent with the expectation of forthcoming revisions or a request to be answered therein. while
Transmittals are typically sent as records, documentation or required materials (such as CAD drawing files) for the project.
Basically Transmittal is the cover page of any submittal for getting approval or record.
kindly i'm adding to your replies that the main different between transmittal and submittal is the submittal general for the project, but the transmittal is specific for one or tow element, activity, or part.