Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What possible measure may be considered in speeding up a delayed project?

Keep in mind a typical construction project.

user-image
Question added by Anisuddin Siddiqui , Sr. Planning Engineer , Southwest Architecture
Date Posted: 2013/09/02
Deleted user
by Deleted user

I guess in construction it will depend on the phase, but it would be safe to say that crashing technique would work, which is basically increasing the amount of resources to finish on time, but there are parts that increased resources would not help, where you could perform other activities / preperations meanwhile (which is the fast tracking technique). Both will increase the cost, unless if you have different resources for the different activities.

Anirban Biswas
by Anirban Biswas , Business Head, Mobility Solutions , GAI Technologies Pvt. Ltd.

Though I'm not in construction projects, but from pure project management perspective, there are2 options - either fast-tracking and/or crashing. In fast tracking, you start the activities parallely which were planned as sequentially. Here the risk is increased. And in crashing, you add more resource to complete the activities faster, which gets added to your cost.

Again, these are just from the books of Project Management, not specifically of construction business.

Thanks!

Faisal Bukhari
by Faisal Bukhari , Project Coordinator , AETCON

Time, Cost and Quality are three basics of the project and are interdependent. If you would like to decrease the time it will effect your cost and quality. i.e. you need to put more cost and your quality may also go down. So always remember three basics of a project and try to understand their interdependencies.

Tanveer Ahmad Niazi
by Tanveer Ahmad Niazi , CEO (Self-employed) , Project Management Training & Consultant

I agree with Tamer, Anirban and Jerry duration and resources are interlinked if you decrease the duration, the resources are increased and if you increase the duration, the resources and decreased. This true but unfortunately not always. We must keep thin mind that sometimes in the construction industry also, we have a case like, “a woman needs  nine months to produce a baby but nine women cannot produce a baby in one month”

Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

U consider

increase of productivity 

resources

pump in more money 

incentivising

subcontracting

split ting the quantum of work in groups or contractors working in parallel

ASARUDEEN SOWKATH ALI
by ASARUDEEN SOWKATH ALI , Planning Manager , Alfanar Construction

Speeding up a delayed project...

1st we have to identify the root cause of the delay whether this delays are happended due to lack of resources / skilled force / non availabilty of front / permit from authorities or other government bodies.

After identified, we have to take the corrective action of the identified matter and make the precautionery measures as a preventive action.

We have to prepare the catchup plan along with the resourse requiremnt and budget required for that.

Because by simply increasing the resources will leads to increase in cost and will affect the company margin so analyse the budget requirement and try to distribute the cost with your client / subcontractor.

1. Increase required skilled work force

2. Daily progress monitoring and gang allocation

3. Offloading of work by distributing the works to subcontractor / agency

4. Motivation program to workforce and staff

5. By providing good bonus or appraisal to the staff who completes the company commitment

6. Arrangement of training programs / meeting to all stackholders to understand the imporrtance of completion in time.

 

Hope the answer for the question

 

Regards,

Asarudeen S.

 

 

 

Jerry Dee
by Jerry Dee , PLANNING ENGINEER , REDCO CONSTRUCTION - ALMANA

There are2 option either use Fastracking or Crashing and both will affect your cashflow and quality.

VIQUAR UDDIN MOHAMMED
by VIQUAR UDDIN MOHAMMED , Senior Planning Engineer , Saudi Real Estate & Infrastructure Company.

By increasing the resources on the activities of the critcal path to the optimum level & start more no of activities parallelly. That would increase the cost but it saves time.

Naina Mohamed Akbar
by Naina Mohamed Akbar , Senior Planner for Riyadh Metro Line 1 and 2 , ThyssenKrupp Elevators

#1: Work overtime

#2: Reallocate resources

#3: Double-check all dependencies

#4: Check time-constrained activities

#5: Swap resources

#6: Crash the schedule

#7: Fast track it

#8: Prevent all scope change

#9: Improve processes

#10: Scale back the scope of work

More Questions Like This