Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

which of the following is the best management tool to determine the longest time the project will take?(WBS-Bar chart -Network diagram-Project charter

user-image
Question added by AHMED SALAH , MEP Projects Manager , CSC Consultant
Date Posted: 2013/04/27
Ahamed Shareef
by Ahamed Shareef , Divisional Head - Quality Assurance , Apollo Tyres Ltd

Network diagram is the tool helpful to identify the longest time project takes. There are many methods, but most familiar is Critical path method.

Detailed activities from WBS must be included in ND with time duration to identify Critical paths/longest durations.

Shejin Varghese
by Shejin Varghese , MEP Engineer , Southern General Services Co. LLC

Critical Path Method Chart, otherwise known as Network Diagram.

Elsayed Ali
by Elsayed Ali , Senior program manager , IBM Middle east and Africa

Network Diagram using critical path method.

Ahmed Montasser Hasan Ibraheem Farag
by Ahmed Montasser Hasan Ibraheem Farag , Project Manager , Rawafed Tech

Network diagram

ASM Rasheduzzaman
by ASM Rasheduzzaman , Cloud Solution Specialist , Microsoft Bangladesh Ltd.

Network Diagram

Adel Raafat
by Adel Raafat , مهندس مشروع , شركة بالمنطقة الشرقيه

Network diagram

kareem kassem
by kareem kassem , Systems Analysis Manager (Middle East and Africa) , IDEMIA

Network diagram

Mohamed Elkhatim Hamada
by Mohamed Elkhatim Hamada , Supply Chain Manager , Central Advance Digitech

Network diagram

mohamed mansour
by mohamed mansour , Planning and Controls Lead Engineer (act as: Project Controls Manager) , Arabian Bemco Contracting co. ltd.

Typically, WBS doesn't contain duration.
Project Charter can only give you limitations, not the real time it should take.
On the other hand, Bar chart and network diagram are two effective tools to represent timing: Bar chart can be effective to see how activities/ tasks are flowing, network diagrams can give the relations and interdependencies, but both cant work separately.
Actually, to control timing, you need to make a blend of them both in a way you can see the flow and durations with the relations visible.
For projects with huge numbers of activities you cant do it manually and you cant see all activities or relations at the same time, so you will need a software that have both Network diagrams and Bar charts like Primavera, Ms project,...etc.

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.