How to install Piggyback CP System for fixed roof tank for a diameter of 200 ft. with 19 columns inside?

As this system should be concentric / circular loop

user-image
Question added by Raghavendra kumar Bondada , Mechanical Engineer , KNPC
Date Posted: 2015/11/23
Bright Matesanwa
by Bright Matesanwa , Boilermaker , GHH Mine Machines

fabricate the flow plate on site then the shell put main hole. mark position of the columns starting from the center going concentric equally spaced then at last put the conical or doomed roof.