It depends on the complexity of the Project.
If it is simple with less number of activities, resources, (ample resources is available, no need of tight resource leveling) MSP is good.
If complexity is more, resources are more in numbers but limited for use, Primavera is Good as the resource levelling and rescheduling is better in that program.