When I click assign for a predecessor or successor on an activity, on the display window, I cannot shrink this "vertical grouping bands". Any info?

user-image
Question added by Wilson Loren , Senior Planning Engineer , Saudi Oger Ltd.
Date Posted: 2015/12/17
Deleted user
by Deleted user

With Primavera P.0, you can collapse or expand task group bands in 'Assign Predecessors' or 'Assign Successors' window/ dialog box but you cannot shrink them as formatting is not available on the modal window. 