Which document provides high-level cost information that is useful when planning for project cost management?

 

A)Project charter

B)Cost baseline

C)project Archive

4) Progress report

user-image
Question added by sardar mardookhy , PMP certified Project manager , MCCI
Date Posted: 2016/01/16
Javad Taghavi
by Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

Project charter, because it includes a summary budget but not in details 

Somen Roy
by Somen Roy , Vice President , Accenture Services Pvt Ltd

Project Charter provides the high level cost information. However, the below inputs are required for deriving the cost management plan.

Project Management Plan, Project Charter, Enterprise Enviornment Factors & Organization Process assets

The derived cost management plan may get revision at various stages of the project, control of the same is a must required skill of an Project management

naeim farahani
by naeim farahani , Planning Engineer , Oil Industries Commissioning & Operation Co.

C is Comprehensive and contain every attach u need to claim or Report or Analyse 

Manal El-Khoraiby
by Manal El-Khoraiby , Client partner / Project Manager , United OFOQ

Project Charter provides High level cost information.

Mahmoud Elsayed Ahmed Shaaban Sallam
by Mahmoud Elsayed Ahmed Shaaban Sallam , civil engineer , Aljaber&Partners

the project charter is a document in project in which contains a board frame detailed description for the project including project budget  project duration, assumption and constrain as it includes business case.

mohammed abduljawad
by mohammed abduljawad , Senior Network and Security architecture , Dr. Soliman FAEEH HOSPITAL

project charter document , It contains the total estimating cost for project in high level.

Zaferullah Sharief, PMP®
by Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Project Charter will be the input for planning Cost Management since it contains the high level budget allotted for the project. 