What is S Curve in Project? Is it the only method to track Progress in Project?

user-image
Question added by Gaurav Singh , Sr. Project Control Engineer , Dodsal Engineering and Construction PTE Ltd
Date Posted: 2016/02/07
Ahmed Khater
by Ahmed Khater , ID& Fit- Out Construction Manager , Harmony Atelier Interior Design& Decoration

A graph of cumulative resources or quantities used in the project against time, and its consider as monitoring tool, tracking is known as fact finding process ( performance reports as cost estimate at completion EAC, project status report, resource loading update and stuffing profile .. etc.

Data collected from tracking are the inputs of monitoring process.

Monitoring technique : S Curve, Earned Value Analysis, Critical Path Analisis 