Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What are the minimum propping period of beams and slabs of various spans?

user-image
Question added by farrukh aziz
Date Posted: 2016/03/10
Mohammed  Ahmed
by Mohammed Ahmed , Sr.Project Engineer , Saudi Electricity Company

It depends. Concrete gains strength at a non-linear rate (Initially high, later low) and at any stage of time, as long as its strength > strength requirements, you don't need any propping. Mostly, during construction, the loads acting on the beams/slabs are 1) Self weight 2) Construction load (or) 3) Weight of upper floor (from the props !) but this is a separate load case

More Questions Like This