what is the basic safty rules and regulation befor the electerical essential loads MDP preventive maintenance startting

user-image
Question added by hassan qutb , Facility&Engineering Manager PMP. , مقاولات خاصه
Date Posted: 2013/09/20
Saifullah Syed
by Saifullah Syed , Material planner/Procurement Specialist , Al khorayef petroleum LLC

Preventive maintenance is done after the working hours or during off day...shut down the main breaker and lock it with lock in off position with tagged Men on work

Nomeriano Bayos
by Nomeriano Bayos , condition monitoring- Electrical/Mechanical , Air liquide philippines

apply work permit system, LOTO the equipment, and make sure that all spareparts and tools needed is available and correct. see to it that the person who is responsible is welltrained and competent.

Ahmed Fathy
by Ahmed Fathy , Business Development Director - MBA - PMP - EBRD International advisor , International Casting & Modern Industries

1- besure thar the source of electricity is off with dont run sign on the switch bord

2-   be sure that the commisioning is ok