Register now or log in to join your professional community.
A. 'PD' can only be used with 'Net Change Planning'
B. 'VM' can only be used in total planning
C. 'PD' triggers a BOM explosion
D. 'VM' can use the forecast for the calculation of the safety stock
Both Option C and D holds good as main features of MRP
PD' triggers a BOM explosion ,,,,,,,,,,,,,,,,,,,,,,,,,,A
Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.