A. 'PD' can only be used with 'Net Change Planning'
B. 'VM' can only be used in total planning
C. 'PD' triggers a BOM explosion
D. 'VM' can use the forecast for the calculation of the safety stock
Both Option C and D holds good as main features of MRP
PD' triggers a BOM explosion ,,,,,,,,,,,,,,,,,,,,,,,,,,A