What are the various levels of documentation in an EPC project?

user-image
Question added by Sanju Plavilaputhenveedu , Sr. QA / QC Engineer , Al Jaber Energy Services LLC
Date Posted: 2016/04/13
Jahabar Sathick
by Jahabar Sathick , Mechanical Engineer , Gulf Industrial service company llc

Following Datas Are Required For Documentation

1.BFD

2.Bid Work Flow

3.CE marketing

4.Commissioning

5.HVAC Abbreviation

6.HVAC Diagram

7.IP

8.ISA

9.NDT

10.P&ID

11.PFD

12.Uniformet

Mariam Jacob
by Mariam Jacob , FBTs for EPPCO, Star Energy, ENOC

1) Engineering Design, IFC Dwgs, BOM

2) Project Schedule & Plan

3) QA project / client based procedures

4) Procurement plan and PO documentation

5) Material QA documentation

6) Material tracking reports

7) As built drawings

8) Project Close Out report.

Rafiq Irman
by Rafiq Irman , Cost Control & Commercial , McConnell Dowell SEA

Front End Engineering Design (FEED), Issued For Construction (IFC) & As Built Drawing

Deleted user
by Deleted user

- engineering design

- material take off

- checking received quotation and information

- preparation technical bid evaluation for clients approval

- material requisition

Sheik Mohideen Jainulabdeen
by Sheik Mohideen Jainulabdeen , Specialist Engineer - Solids Handling & Package Unit , Tecnicas Reunidas

In an EPC phase of projects, there are Five (5) phases of document submissions namely% Engineering Package,% Engineering Package,% Engineering Package, IFC (Issued for Construction) Package and As-Built Package. Each phase of documents quality and additional details may vary based on the progress of the projects. 

The best practice in the EPC industry to handle engineering deliverables based on categorization by Engineering discipline-wise. Please refer the below list of categorization:

1. General Engineering Data, which contains the documents like Engg. Design Data, Project Schedule, Equipment List, etc.

2. Process Deliverables, which includes Process Design Philosophy, PFD, P&ID, Process Design Data, Process Equipment List, HMB, Utility List, Line List, etc.

3. Equipment/Mechanical Deliverables, which includes General Spec., GA Drawing, Datasheet, Material Requisistion, TBE Report, etc. 

4. HSE Delievrables, which contains safety report, HAZID Report, HAZOP Report, Fire water related documents, Noise Map & Report, etc.

5. Civil Deliverables, whcih includes Civil design spec., Foundation drawing, Drainage details, Civil MTO, Steel Structure Drawings, etc.

6. Plant Layout Deliverables, which includes Plot Plant, Layout Design Spec., etc.

7. Piping Deliverables, which contains Piping Installation documents, Piping Stress Analysis documents, PMS, Material & Corrosion documents, etc.

8. Instrumentation & Control Deliverables, which includes Instrument Spec., Control Narrative, Functional Drawing, Instrument Wiring Diagram, Instrument Loop & Logic Diagram, etc.

9. Electrical Deliverables, which contains Elec. Design Spec., SLD, Cable Tray Layout, Elec. MTO, Cable List, Elec. Calculation, etc.

. Quality & Inspection Deliverables, which contains QA/QC Documents, Inspection & Test Plan of all Equipmens, etc.

I hope the above list of Engineering deliverables might be useful for all. If any correction on the same, please correct me. 

Gustavo Arguello
by Gustavo Arguello , PMO Project Manager , Vopak

1.-Engineering Design

2.- Project Schedule

3.- Procurement Plan

4.- Construction Plan

5.- QA/QC Plan

6.- ESH Plan

7.- Precommissioning and Commissioning

Amalendu Samanta
by Amalendu Samanta , IOT Infrastructure & Energy Services Ltd

Project's Job Procedure (ITP,QAP)

Sreebha Sumesh
by Sreebha Sumesh , Quality Assurance officer , Broadway bakery

documentation process

four levels

Quality manual

Operational procedure sop

work instruction

Other documents including training report

yogesh Diwane
by yogesh Diwane , Operations & Facility Manager , Seraj power services

There are four level in EPC 0 , 1 , 2 and 3

JULIUS RECON
by JULIUS RECON , QC Document Engineer , Atlantic, Gulf and Pacific Company of Manil

There are Four Levels of Documentation in an EPC:

Level 1 : Quality Manual - overview of the company, its products and services, scope and organization and its responsibilities

Level 2 : Quality Procedures - is the processes and interdepartmental controls that address the ISO 9001 requirements.

Level 3 : Work Instructions - mainly it explains the details of activities; how it should be performed. It includes plans, drawings, manuals, flow charts, product specifications and many more.

Level 4 : Other Documents - Forms, labels, tags, and other documents that prompt the recording of evidence of compliance to requirements.

 

When your company have these 4 levels of documentation, we can say that you have a good and decent documentation and procedure in your company.