Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is a computer-driven system for analyzing and projecting materials needs and then scheduling their arrival the workstation at the right time?

   1. JIT   2. CAD   3. material requirement planning   4. CAM

user-image
Question added by Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG
Date Posted: 2016/04/22
د Waleed
by د Waleed , Management - Leadership-Business Administration-HR&Training-Customer Service/Retention -Call Center , Multi Companies Categories: Auditing -Trade -Customer service -HR-IT&Internet -Training&Consultation

Material requirements planning (MRP) is a production planning and inventory control system. It is the correct answer .

 

Thank You

Saiyid Maududi-Oracle Applications Consultant
by Saiyid Maududi-Oracle Applications Consultant , Entrerprise Architect , US Technomatrix, Inc

Hello Team,

To contend with lengthening supply chains, limited supplier capacity, and retailers’ demands for early delivery, Sport Obermeyer undertook a variety of quick-response initiatives to shorten lead times. First, the company slashed the time it took to process orders and compute raw-material requirements by introducing computerized systems to support those activities. Second, because lead times for obtaining raw materials proved difficult to shorten, the company began to anticipate what materials it would require and pre-position them in a warehouse in the Far East. With materials in hand, Sport Obermeyer was able to begin manufacturing as soon as it received orders. Third, as delivery due dates approached, the company turned to air freight to expedite delivery from the Far East to its Denver distribution center. By 1990, those changes had reduced delivery lead times by more than one month.

Regards,

 

Saiyid

Ghada Eweda
by Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

The correct answer is 

3- material requirement planning.

I apologize for the answer, I leave the answer to experts specialists in this field, this is not my area.

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

MRP - Material Requirement planning is the right answer.

material requirement planning____________Answer

Option 3) is answer ______________________