The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as_?

A.     duration

B.     total flat

C.     free float

D.     interfering float.

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/04/25
Usman Islam
by Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

free float is the correct answer...........

TARIG BABIKER AL AMIN
by TARIG BABIKER AL AMIN , Head of Planning and Studies Unit , Sudanese Free Zones and Markets Co.

B : is the right answer - Total float : is the amount of time that an activity can be delayed without delaying the project completion date , because C : Free float : is the amount of time that an activity can be delayed without delaying the Early Start of its successor activity

Ahmed Mohamed Ayesh Sarkhi
by Ahmed Mohamed Ayesh Sarkhi , Shared Services Supervisor , Saudi Musheera Co. Ltd.

Free Float Option " C "              .

Rami Assaf
by Rami Assaf , loading and Storage Operations Supervisor , Arab Potash Company

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?

3. free float

 

Mohammed  Ashraf
by Mohammed Ashraf , Director of International Business , Saqr Al-Khayala Group

It shows option "C" is suitable one. 

sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

Free float...is the answer

mohamed abd el hamid abd alla elfarran elfaran
by mohamed abd el hamid abd alla elfarran elfaran , مهندس مدنى , مكتب العطيشان الهندسى

..................   c .      free float

Yaqoub Alomar
by Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality

C.     free float

*****************

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

The correct answer is option (C.free float)

Amr Gamal Anwar Hassan
by Amr Gamal Anwar Hassan , مهندس حاسب كميات , Shurfah Real Estate Development and Investment

I think the correct answer is C.free float

 

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,,

my choice is option C