Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

For completion of a project, the critical path of the network represents_.

A.     minimum time

B.     maximum time

C.     maximum cost

D.     minimum cost.

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/04/27
ghazi Almahadeen
by ghazi Almahadeen , Project Facilitator , Jordan River Foundation

Thanks for the invite ......................... D. minimum cost.A. minimum time...

emad namdar
by emad namdar , deputy of general director , Iraqi atomic energy commission- ministry of military manufacturing

Critical path represent minimum time of execution the project

Mahmoud Zaher Tarakji
by Mahmoud Zaher Tarakji , مدير , أوال جاليري

............A AND ....D...............

Yahia mohamed  Amen Gad
by Yahia mohamed Amen Gad , إدارة - مدرب - , سنابل الأجيال للتعليم والتدريب

Thank you for your call / a

Omar Saad Ibrahem Alhamadani
by Omar Saad Ibrahem Alhamadani , Snr. HR & Finance Officer , Sarri Zawetta Company

Thanks

It is A & D................

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

The Answer is ...A. minimum time

Wasi Rahman Sheikh
by Wasi Rahman Sheikh , WAREHOUSE SUPERVISOR , AL MUTLAQ FURNITURE MFG

Answer is option D) <<<<<<<<<<<<<<<<<<<

ASIF BE Mech IEng PMP
by ASIF BE Mech IEng PMP , Projects Manager - Buildings Utilities & infrastructure , Qatar General Electricity & Water Corporation

In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project

Mohammed Abdelseed
by Mohammed Abdelseed , Maintenance Operations and Technical Support Section Head , Bashayer Pipeline Company

the Answer is "B", Critical Path is the longest path in the project net work, it will be calculated based on 'AOA", AON" -Critical Path method.

Abdullah Altuwayjiri
by Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

B.     maximum time

to be more accurate, it is the path that if any of its task get delayed by a specific time, the whole project will be delayed by the same amount of time

sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

"A" minimum time,

thanks....

More Questions Like This