A. minimum time
B. maximum time
C. maximum cost
D. minimum cost.
Thanks for the invite ......................... D. minimum cost.A. minimum time...
............A AND ....D...............
Thank you for your call / a
Thanks
It is A & D................
The Answer is ...A. minimum time
Answer is option D) <<<<<<<<<<<<<<<<<<<
In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project
the Answer is "B", Critical Path is the longest path in the project net work, it will be calculated based on 'AOA", AON" -Critical Path method.
B. maximum time
to be more accurate, it is the path that if any of its task get delayed by a specific time, the whole project will be delayed by the same amount of time
"A" minimum time,