A)
Use creative pricing to modify demand
B)
Build anticipation inventory to absorb the variability in demand
C)
Increase overtime to satisfy peaks in demand
D)
Use promotional campaigns to boost demand
Ans: C) Increase overtime to satisfy peaks in demand.
Justification : This is a reactive strategy and certainly also a chase strategy to satisfy increase in demand.
agree to the reply given by Md. Fazlur Rahman
Yes, Option C is the right answer , because from the given options, only overtime to meet demand is reactive and other three are plans to achieve improvement
Thanks
It is all of above .........................
thanks for the invitationThe answer could be to use more than one strategy, including
B)
Build anticipation inventory to absorb the variability in demand
The Answer is
C) Increase overtime to satisfy peaks in demand
all above options .
I apologize for the answer I leave the answer to the experts, specialists in this field that's not my specialty field.
Hello Team,
The marketing planning process involves forging a plan for a firm's marketing activities. A marketing plan can also pertain to a specific product, as well as to an organization's overall marketing strategy. Generally speaking, an organization's marketing planning process is derived from its overall business strategy. Thus, when top management are devising the firm's strategic direction or mission, the intended marketing activities are incorporated into this plan. There are several levels of marketing objectives within an organization. The senior management of a firm would formulate a general business strategy for a firm. However, this general business strategy would be interpreted and implemented in different contexts throughout the firm.