Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

How can this be best described in project management terms as? See below for details and options.

You have just collected project information from stakeholders and are analyzing their input with the project team. One stakeholder is worried about whether the organization has the proper skill sets in house to deliver the product of the project. 

a. A constraint

b. A potential risk

c. An issue

d. A and C

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/11
DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Option b is absolutely right answer.

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

option B,,,,,,,,,,,,,,,,,,

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D – This is not exactly a trick question, but it's close. The scenario described is not only a constraint (no

internal headcount with the skill set), but it is also an issue (if I need additional headcount, how do I go

about obtaining it?)

sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

I think B is the answer,..

Thanks for invite

More Questions Like This