process there was a disagreement between the members of the technical team regarding what had to be built to satisfy a user requirement. As a result, some of the technical team members created features in the deliverable that the customer did not really ask for. What would have specifically helped to avoid this situation?
a. Requirements management plan
b. Requirements traceability matrix
c. Scope statement
d. WBS
Thanks for invitation..... c. Scope statement
Thanks,
Option 3.....................
Option " C " .
thanks for invition ,,,,,,,,,, my choice is option C