While the organization was thinking about erecting a modular structure, they decided on a more traditional approach. The foundation will be poured and cured before the framing begins. This is an example of:
a. Discretionary dependency
b. Mandatory dependency
c. External dependency
d. Internal dependency
Mandatory dependency,
Thanks for invite
I answer is only B. The foundation must set before you can start erecting the walls of the structure.
thanks for invition ,,,,,,,,,, my choice is option B