Your project is experiencing resource constraints at certain times in the project timeline, Refer to below options for answer?

requiring you to adjust start and finish dates on the schedule. What tool is best to use in this situation?

 

a. Resource leveling

b. Feeding buffer

c. Critical Path method

d. Resource smoothing

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/15
Waleed Hamdy
by Waleed Hamdy , MEP PROJECTS CONTROL HEAD SECTION , AZMEEL CONTRACTING COMPANY

a. Resource leveling ............