Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

A finish to finish relationship is defined as which of the following?

 

a. Both activities have to finish at the same time

b. The predecessor has to finish before the successor can finish

c. Both activities are on the critical path

d. The predecessor has a defined lead while the successor has a defined lag

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/16
Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

No.B ..............   a Successor Activity cannot finish until a Predecessor Activity has finished

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option A

Ghada Eweda
by Ghada Eweda , Medical sales hospital representative , Pfizer pharmaceutical Plc.

Agree on expert answers. Thanks

Abdullah Altuwayjiri
by Abdullah Altuwayjiri , PMO Analyst , Qassim University - GDPM

a. Both activities have to finish at the same time

VINOD KUMAR
by VINOD KUMAR , Manager-Planning and PMO , Voltas Limited

Both activites have to finish at same time irrespective of their start dates.

sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

I agree with A option...........

Usman Islam
by Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

A is the correct answer ...........

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B - This is the definition of a finish to finish relationship: I must complete activity ‘a’ before I complete

Activity ‘b’

More Questions Like This