Register now or log in to join your professional community.
expressed concerns about the size of the budget. As the project manager, you coach the stakeholders by telling them that the project is being undertaken as a progressive elaboration. As a result, the initial budget estimate covers a wide range of+/-% because not a lot is known about the project yet. This type of estimate is known as:
a. Budget estimate
b. Rough order of magnitude estimate
c. Definitive estimate
d. Predictive uncertainty estimate
A correct answer is alreday given by experts.thanks
thanks for invition ,,,,,,,,,, my choice is option B
B - +/-% is the definition of a rough order of magnitude. A budget estimate is -% to plus%. A definitive estimate is +/ -%, and a predictive uncertainty estimate is a made-up term.
B Option,
Thanks for invite................
................. b. Rough order
I apologize for the answer I leave the answer to the specialists the experts in the this field that's not my area.