The project team has done outstanding work on a current project. While the stakeholders are satisfied with the product of the project,...

they have been consistently whining about the cost and have asked you, the project manager, to review options that would help reduce costs on the project. Given that this scope has been reduced to the most essential must-have items, where are your best options for reducing costs?

a. Fixed and variable costs

b. Direct and indirect costs

c. Direct and variable costs

d. Fixed and indirect costs

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/18
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C – The costs that you can best control are costs that directly impact your project (direct costs), and variable costs (contract resources that work hourly). You have less control over fixed and indirect costs.

Eng Ahmed Elsharkawy
by Eng Ahmed Elsharkawy , Civil Engineering Project Manager , Altwijry office

thanks for invition ,,,,,,,,,, my choice is option C