Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which performance index describes the cost projection of the remaining work that must be achieved to meet the goals of the project?

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/05/18
Imran khan, PMP
by Imran khan, PMP , Project Engineer/ Project Manager LV/LC , Engineering Consultants Group (ECG)

CPI is the cost performance index that tells you what is the status of the project, while TCPI would give you the performance index at the completion of the project therefore you are right! its a definition to TCPI. A

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A – This is a definition of the To Complete Performance Index (TCPI)

sardar mardookhy
by sardar mardookhy , PMP certified Project manager , MCCI

C option,

Thanks for invite...

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.