The forward pass is used to determine Earliest Start Time (EST) and Earliest Finish Time (EFT) of tasks. The EST of a task is the _ of the EFT of all preceding tasks? 1- Average 2- Minimum 3- Maximum 4- Sum

user-image
Question added by KHALED ALABOUDI , US TAX ADVISORY , US TAX GLOBAL SERVICE LLC
Date Posted: 2016/05/31
MahmOud SaLama
by MahmOud SaLama , Software Tester , Al Qemam For Programming

The EST of a task is the Maximum of the EFT of all preceding tasks