Which of the following processes is involved with identifying which quality standards are relevant to the project and devising a plan on?

how to meet / satisfy these standards?

A. Perform quality assurance

B. Quality planning

C. Perform quality control

D. None of the choices are correct

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/06/16
sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

B. Quality planning

Thanks for invite.........

Sathish Prabhu.V
by Sathish Prabhu.V , Manager - Operations & Process Improvement , Revolution Valves

Quality planning should be the apt answer

Deleted user
by Deleted user

Correct answer is 

B. Quality planning

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

I prefer to leave answers to Experts. Thanks for Your kind Invitation.