A. Quality Assurance
B. Quality Control
C. Quality Planning
D. Quality Review
Monitoring results against standards are called QUALITY CONTROL.
B. Quality Control...............
it is a process of Quality control
where the characteristics of the product is monitored to assure that it comply the requirements
Thanks, b is the good answer.
My opinion is that the right answer is:B. Quality Control
It is B - Quality Control . This is the process through which project results or product is measured and determined whether they comply with quality standards.
Correct answer is
B. Quality Control
Thanks for invitation
----------------B. Quality Control--------------------
B. Quality Control
Quality Control (Assurance and Audit are part of quality control activities)
Quality Control is the apt answer and is part of Quality Assurance.