A WBS dictionary is a document which…?

a-describes technical terms used for scope management.

b-describes the details for each component in the WBS.

c-translates essential WBS terms for global project teams.

d-helps translate functional into technical requirements.

user-image
Question added by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
Date Posted: 2016/06/29
Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

b-describes the details for each component in the WBS.

 

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

A W.B.S ( WORK BREAK DOWN STRUCTURE)dictionary is a document that provides a detailed information about each element in the WBS, including work packages and control accounts .,

Hossam hemdan abou-elhassan
by Hossam hemdan abou-elhassan , construction civil engineer , ROAYA GROUP FOR DEVELOPMENT AND PROGECTS MANAGMENT

WBS it useful  to prepare project plan,identifying activities,scheduling,identifying cost and schedule at various level and time and cost control 

so option  B is correct choice

Usman Islam
by Usman Islam , Logistics And Warehouse Manager , Kirtanlal Scaffolding & Formwork

Option B is the right choice

Piotr Teteruk
by Piotr Teteruk , IT Project Manager Roche , Roche

The Work Breakdown Structure (WBS) provides a structural view into the project. It is an essential tool for planning and executing the project. The WBS is a useful resource for project management and should be consulted for relevant information on each component of the WBS. Included in the WBS description can be: a brief definition of the WBS element (function, deliverable, etc.) associated activities, milestones, and other information such as performance measurement criteria, statement of work paragraph number, contract line item, start and end dates, resource requirements, cost estimates, quality requirements, technical content, contact information, and revision history.  A WBS Dictionary contains more detailed information about elements within a Work Breakdown Structure (WBS).

A WBS dictionary is a document which describes the details for each component in the WBS .

Deleted user
by Deleted user

I will go for Option B.

WBS Dictionary is a document that describes each component in the WBS.

For each component the WBS Dictionary includes a brief scope description,defined deliverables,list of associated activities and sometimes other information.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

b - describes the details for each component in the WBS.

It is a document that supports WBS - details of what needs to be done are found in WBS dictionary.

روان حؤبش
by روان حؤبش , Head of Training,Continuous Education & Community Service Unit , Arab Open University - Jordan Branch

B.describe the details for each component in the WBS

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Option b- is the most appropriate answer

Kevin McCarthy
by Kevin McCarthy , Proposals Engineer , WTS Broadcast Systems

b-describes the details for each component in the work breakdown structure.

Deleted user
by Deleted user

Thanks for invitation -