Register now or log in to join your professional community.
a) The risk is less as it is divided between the paths
b) The risk is more as the risk of delay is more
c) Risk depends on how the critical path is calculated
d) There is no risk as the paths cancel it out
My answer is:
b) The risk is more as the risk of delay is more
My answer is (b)
*****************
Agreed with Ksenija Kancetak answer
Ans: (B) Higher Risk [From Systems Engineering perspective: If a system consists of two components each having reliability of 90%, than the reliability of the system will be 0.90 x 0.90 = 0.81 i.e. 81%. Now consider each critical path as one component, system as the project and reliability as the Risks associated with the critial path. So as you will keep adding more components (aka critical paths), reliability of overall system (Project) will go down even if the risks of each critical path is same.
Thanks for your invitation. I think the mutiple critical paths in a project as :
1- Risk of the Engineering system
2- Risk of components reliability of the Integrating System
3- Delay in the execution stages
4- Big damage in the deliveries
b) The risk is more as the risk of delay is more is the correct answer, which was practically experienced by me twice.
because each project have so many tasks and every task is composed of so many activities the shortest time to complete the task is called critical path for that task so for many tasks then the critical path is the shortest time to complete the project you can even plot adigram to find the critical path of every tacsk and the critical path of the whole project
Answer : b) The risk is more as the risk of delay is more
Since critical path increases the risk, more the critical paths more the risk.
Option b- is the most appropriate answer
c) Risk depends on how the critical path is calculated.