Make payment to seller is done in _?

 

A. Plan Procurements

B. Conduct Procurements

C. Administer Procurements

D. Close Procurements

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/03
Md Fazlur Rahman
by Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

C. Administer Procurements

Payment is a part of procurement process and therefore it is Administer procurements.  Close procurement will occur after distribution of goods from warehouse to intended users.

Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

My opinion is that the right answer is:

C. Administer Procurements

VINAY KUMAR GOSWAMI
by VINAY KUMAR GOSWAMI , Partner , 2MI

Option C - . Administer Procurement (It is part of managing life cycle of procurement).

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

Thanks for invitation....I endorse answers given by colleagues &Experts

Deleted user
by Deleted user

My vote also goes to

C. Administer Procurements

sardar mardookhy
by sardar mardookhy , Head of portfolio management department , MCI

C. Administer Procurements

Is my option

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is C

Making payment to seller is an integral part of contract / procurement administration.

Ramzi SAMRI
by Ramzi SAMRI , Industrial engineer , Institut für Betriebliche Bildungsforschung Berlin (IBBF)

I agree with experts, C is the correct answer

Ahilan R
by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

Once the seller supplied the materials along with invoice, test certificates /related documents and acceptd by purchaser.

mamoun mokhtar
by mamoun mokhtar , general manager , albyan technical foungary

officially all payments should be done by the cashier after the seller present the authorities documents and signatures to him or if not possible then by procurement administrator