From where to remove the formwork of cantilever beam? from support or from free end?

user-image
Question added by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)
Date Posted: 2016/07/05
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Cantiliver beam is having maximum load ( Share Force & Bending Moment) at its support.

So this is essential to remove formwork of cantiliver beam from its free end to avoid any accident if concrete does not properly haden. It is better to keep some vertical support under the support of cantiliver beam until it completely harden after 28 days.

Nelio Beleo
by Nelio Beleo , Civil Inspector , Petrojet

We start removing formworks of cantilever beams from its free end (bracings and sideforms) and the last part is the supports & bottom forms