Register now or log in to join your professional community.
A. firm fixed price
B. None of the other alternatives apply
C. fixed price plus incentive fee
D. letter contract
E. cost plus percentage of cost
The process of change will be same in all contracts. However if you wish to increase the scope, response will be
Option - E (Vendor will easily agree to change the scope as he can make more economic gains)
However, it would be better to cancel the contract and sign another contract if there is decrease in scope.
My opinion is that the right answer is:
E. cost plus percentage of cos
Option-E is appropriate choice.
it is easy to change contract scope if it is beneficial to the contractor (flexible contracts )
E. cost plus percentage of cost is teh answer....
Thanks