Job Safety Assessment (American) is where you have to breakdown/enumerate all the procedures for the work and for each have to be discussed the safety measures and precautions,

while Risk Assessment (UK) is where you have to distinguish all the possible hazards while performing the work, and evaluate them and provide  safety measures and precautions.