Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?

 

A. Cost Plus Incentive Fee

B. Firm Fixed Price Plus Incentive

C. Firm Fixed Price

D. Cost Plus Fixed Fee

E. Cost Plus Percentage of Costs

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/22
Ksenija Kancelak
by Ksenija Kancelak , Construction Project Manager , City of Koprivnica, Koprivnica (Croatia)

The right answer is:

B. Firm Fixed Price Plus Incentive

 

More Questions Like This