Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What are the points to be considered while selecting precast structures for multi storey building?

user-image
Question added by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)
Date Posted: 2016/07/29
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Precast concrete is not recommended in multi-storey buildings specially foundations, columns and beams. The following are considerations while choosing precast structure elements in multi-storey buildings.

1) In high and medium Seismic Area, it should be avoided.

2) Only Precast slabs are used where spans are medium in multi-storey buildings.

3) when floors are having heavy live & impact  loads and  vibration, even precast slab should not be used.

4) MEP works should be properly design before starting fabrications of precast elements to avoid cutting of precast concrete which can be dangerous.

5) The surrounding area should be clear for crane to lift heavy elements of precast concrete.

R MANESH RAVEENDRAN NAIR
by R MANESH RAVEENDRAN NAIR , site engineer( job performer) , NASAR SAID AL HAJRI

1.ensure the pre cast element is free from damages or craks

2.ensure the pre element strenth is already acheeved(according to cube test report)

3 while erecting pre cast column, ensure the alignment and plump 

Ignacio Llobet Azpitarte
by Ignacio Llobet Azpitarte , Project Manager , New Company GDO

Continuity of supply is the main question to answer

More Questions Like This