Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following is NOT an input of the Contract Administration process?

 

A. Selected Sellers

B. Contract Management Plan

C. Procurement Management Plan

D. Work Performance Information

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/07/29
Nader Ali
by Nader Ali , Technical office manager , AlSafwa Contracting

The answer is C) Procurement Management Plan

Mohamed Helal
by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL

B. Contract Management Plan