What are the lists of delays that are compensable from the client by its contractor?

user-image
Question added by Nelio Beleo , Civil Inspector , Petrojet
Date Posted: 2016/08/03
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Following are some compensable delays• Owner’s failure to furnish the site to the contractor by an agreed date

Faulty design

 

Incomplete drawings and specifications

 

Changes in scope

 

Suspension of work

 

Differing site conditions

 

Late delivery of owner-supplied materials

 

Mohammad Hasan Annuari
by Mohammad Hasan Annuari , Project Support Engineer , Private contractor

Climate, Accidents, Unavailability of materials and call of nature.