In which process is formal acceptance and handover of the final product/ service performed?

 

A. Contract closure

B. Scope verification

C. Close project

D. Contract administration

 

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/06
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The most suitable option is

C. Close project

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-A Contract Closure

Contract closure is concerned with completing and settling the terms of the contracts let for the project. It supports the project completion process because the contract closure process determines if the work described in the contracts was completed accurately and satisfactorily