Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the difference between the lage and Lead at time management in construction projects?

user-image
Question added by Hossam hemdan abou-elhassan , construction civil engineer , ROAYA GROUP FOR DEVELOPMENT AND PROGECTS MANAGMENT
Date Posted: 2016/08/07
appa anand badipetla
by appa anand badipetla , Deputy Manager-Designs , PES ENGINEERS PVT Ltd

Lag and Lead_

Lag : The amount of time the successor activity can be delayed with respect to a predecessor activity is Lag.

Lead : The amount of time the successor activity can be advanced with respect to a predecessor activity is lead.

safi eljim bousaada
by safi eljim bousaada , Senior project manager, certified PMP, PSM-I, PSPO-I , Saphir Consult

A lead is the amount of time whereby a successor activity can be advanced with respect to a predecessor activity. So in this case the second task can start N days before the end date of the first task.A lag is the amount of time whereby a successor activity will be delayed with respect to a predecessor activity. In this case the second task can start only N days after the end date of the first task.

Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Lag

The amount of time whereby a successor activity will be delayed with respect to a predecessor activity.

For example: When building two walls from a novel design, one might start the second wall 2 days after the first so that the second team can learn from the first. This is an example of a lag in a Start-Start relationship.

Lead

The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.

For example, on a project to construct a new office building, the landscaping could be scheduled to start prior to the scheduled punch list completion.

 

More Questions Like This