Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

In resources levelling?

  (A) Total duration of project is reduced

 

(B) Total duration of project is increased

 

(C) Uniform demand of resources is achieved

 

(D) Cost of project is controlled

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/08
Ahilan R
by Ahilan R , Scientific Assistant-D , Nuclear Power Corporation of India Ltd (NPCIL)

i endorse MD RASHID RAZA's answer

Yahya Bah
by Yahya Bah , Principal & Marketing Consultant , International Community

This is a common term used in project management. It is a technique for adjusting start and deadline dates arising from resource constraints in order allign demand to supply. 

In a nutshell, it helps in the effective coordination resources to ensure that supply meets demand in the event of constraints by adjusting deadlines.

MD RASHID RAZA
by MD RASHID RAZA , qa/qc civil engineer , Arkitechno consultant india limited

In resources levelling is a technique in which start and finish dates for any activity are adjusted in accordence with the availibility of resource and material.

More Questions Like This