Register now or log in to join your professional community.
(A) The detailed estimated cost based on detailed design
(B) The several alternatives of the project that have been considered
(C) The soil survey, traffic survey, concept design and approximate cost
(D) The contract documents for inviting tenders
Prepare narrative report for the preparation of Baseline Schedule. This narrative report contains employer's Requirements of the Project including stakeholder Requirements.
the detailed estimated cost based on detailed design ,The soil survey, traffic survey, concept design and approximate cost
(B) The several alternatives of the project that have been considered &
(C) The soil survey, traffic survey, concept design and approximate cost
Answer is D.)the contract documents for inviting tenders.(technical proposal financial, management and administrative proposal, including costing, planning, work breakdown structure, etc. All this comes under the is tender...so,other options are involuntary)