In PERT analysis, the time estimates of activities and probability of their occurrence follow?

(A) Normal distribution curve

(B) Poisson's distribution curve

(C) Beta distribution curve

(D) None of the above

user-image
Question added by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia
Date Posted: 2016/08/08
Mohamed Hamed
by Mohamed Hamed , Continuous Improvement Specialist (Black Belt) , Woodward Inc

C) Beta distribution curve