Register now or log in to join your professional community.
a-Baselines in system configurations are often also referred to as deltas.
b-In configuration management, baselines are used to control change.
c-Project management baselines are used for performance measurement.
d- In project management, baselines help assess variance and trends.
The concept of baselines is central to an effective configuration management program; it is however, not a unique configuration management concept.
A baseline is a reference point in the software development life cycle marked by the completion and formal approval of a set of predefined work products.
Baselines are also used to identify the aggregate of software and hardware components that make up a specific release of a system.
The baseline in project management refers to the initial cost, scope and schedule of the project. The baseline functions as a measure so the project will not deviate.
Usually baseline values in PM will be:
- Original Scheduled Start and Finish Dates
- Planned Effort (may be expressed in hours)
- Planned or Budgeted Cost
Option C : project management baselines are uased for performance measurment.
It's true. Baseline is used in both disciplines. In PM it's used to track changes in scope.
Thanks
It is A .....................
Option-A Baselines in system configurations are often also referred to as deltas
The following statement is not true;
a-Baselines in system configurations are often also referred to as deltas because: In configuration management, baselines refer to a fixed reference point that represents the state of a system or product at a specific moment. Deltas, on the other hand, refer to the differences or changes made from one baseline to another, not the baseline itself. Therefore, baselines are not referred to as deltas.