All of the following statements are true regarding the request seller responses process EXCEPT?

A. The process is a part of the project executing process group

B. The output of this process include proposals and qualified sellers list

C. The process involves obtaining responses from prospective sellers on how project

requirements can be satisfied

D. The tool/technique of this process are weighting systems, independent estimates, and screening systems

E. The prospective sellers, normally at no direct cost to the project, expend most of the actual effort in this process

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2016/08/14
Imran Ahmed
by Imran Ahmed , Manager-Planning & Delay Analyst , Nesma United Industries (NUI) Saudi Arabia

Option-D  The tool/technique of this process are weighting systems,independent estimates, and screening systems